Party Wall Case Law Gyle-Thompson v Wall Street
Party Wall Case Law Gyle-Thompson v Wall Street is a Chancery Division decision from 1974 that still resonates across party wall practice. It tackles three evergreen questions: (1) what the statutory rights actually allow a building owner to do to a party fence wall, (2) when an award is vulnerable because it purports to authorise something the statute does not, and (3) how strictly the service and appointment procedures must be followed. Brightman J granted an injunction restraining demolition and made clear that demolish and rebuild did not include a unilateral right to lower a party fence wall under the then London Building Acts (Amendment) Act 1939; an award that said otherwise was ultra vires and void.
Background - Party Wall Case Law Gyle-Thompson v Wall Street
Wall Street (Properties) Ltd owned a former warehouse site behind Paultons Square, Chelsea. Planning permission had been granted to redevelop with houses, flats and offices. The warehouse’s west wall abutted the rear gardens of the Paultons Square houses. Once the other three warehouse walls were demolished, the west wall ceased to be part of a building and became a party fence wall along the boundary. The developer wanted to reduce the wall’s height substantially to improve light to the new scheme.
Wall Street’s surveyor, our very own Mr John Anstey, and the householders’ (informally appointed) surveyor, Mr V.F. Johnson, engaged in correspondence and site meetings from early 1972. Initial “party structure notices” were served in February 1972 describing “partial demolition and rebuilding” for connection to new works; an interim award in June 1972 permitted shoring and repair to render the wall safe pending redevelopment. Negotiations then shifted to a redesigned proposal: demolish and rebuild to 19 feet with groups of obscured slit windows in the upper portion - still a reduction of about 9 feet from the existing 28 feet. The adjoining owners objected.
Late in 1972 the developer sought to restart the statutory route. New notices dated 20 December 1972 proposed demolition and rebuilding of the party fence wall at 19 feet. Critically, these notices were sent only to Mr Johnson, not to the adjoining owners themselves. With Mr Johnson’s concurrence, Mr Donald Ensom was asked to act as third surveyor. On 2 March 1973, Mr Ensom signed an award (previously signed by Mr Anstey) authorising the reduced-height fenestrated wall. The owners did not file a county court appeal within the 14-day period from “delivery” of the award as set out in the 1939 Act. On 17 March 1973, demolition began; the plaintiffs obtained an urgent injunction.
The statutory framework (then and there)
The case turned on the London Building Acts (Amendment) Act 1939. Section 46(1) conferred various rights in respect of party walls and party fence walls. Two paragraphs mattered:
- s.46(1)(a) - a right to “make good, underpin, thicken or repair or demolish and rebuild” a party structure or party fence wall where necessary due to defect or want of repair; and
 - s.46(1)(k) - a right to raise a party fence wall, to raise and use it as a party wall, or to demolish and rebuild a party fence wall as either a party fence wall or party wall.
 
Section 47 required a party structure notice before exercising s.46 rights, and section 55 provided the dispute resolution machinery: each party appoints a surveyor (or agrees one), those surveyors select a third surveyor, and an award is conclusive subject to a 14-day county court appeal. Importantly, appointments and selections had to be in writing.
The issues before the court
- Substantive right: Did s.46 entitle the building owner to demolish and rebuild to a lower height (i.e., to reduce the wall) without the adjoining owners’ consent?
 - Conclusive award? If an award purports to authorise that reduction, is the adjoining owner’s sole remedy a 14-day county court appeal, or can the High Court intervene where the award is ultra vires?
 - Procedure: Were the December 1972 notices validly served and were the surveyors properly appointed in writing such that the third surveyor and the award had jurisdiction?
 - Delivery and timing: When was the award “delivered” for the 14-day appeal period, and what practical standards should surveyors follow?
 
The court’s reasoning
1) No unilateral right to lower a party fence wall
Brightman J held that under the 1939 Act there was no express right to reduce the height of a party fence wall. Although the statute allowed “demolish and rebuild”, the judge read this as an authority to rebuild to the same height, absent clear wording to the contrary. He relied on the Court of Appeal’s approach in Burlington Property Co v Odeon Theatres Ltd (decided under predecessor legislation), which rejected changing the form of a party structure under the guise of rebuilding. Reducing height would effectively expropriate the adjoining owners’ property rights, something Parliament would be expected to authorise in clear terms if intended. It had not.
The developer argued that s.46(1)(k)’s allowance to “demolish a party fence wall and rebuild it as a party fence wall” must include changing form, otherwise it added nothing beyond s.46(1)(a). The judge disagreed: owners might wish to rebuild for reasons other than defect or disrepair (e.g., better materials, reflective finishes), yet still to the same overall envelope. That rationale gave s.46(1)(k) content without implying a right to lower. The argument for an implied right to reduce failed.
Bottom line: Under the 1939 Act you could not lawfully rebuild a party fence wall at a lesser height without consent or express statutory authority.
2) Award ultra vires; High Court jurisdiction despite “conclusive” wording
Could the plaintiffs be shut out because they did not appeal to the county court within 14 days? No. The judge held that the surveyors had no power to determine a “right” that did not exist in the statute. An award that purported to grant such a right was ultra vires and invalid. Where an award exceeds the statutory jurisdiction, the High Court can intervene (by injunction) notwithstanding the conclusive-award/appeal provisions. The judge drew support from In re Stone and Hastie (under earlier London legislation), which treated an award as a nullity where surveyors purported to decide something outside their statutory remit.
Brightman J explained that s.55 allowed surveyors to “determine the right to execute” where the statute already granted a conditional right (e.g., whether necessity existed for works due to defect), not to conjure new rights beyond the Act. Here, because the 1939 Act did not grant a right to reduce, the award could not validly determine that the developer did have such a right.
3) Procedural defects: invalid service and appointments voided the award
Even if the court had been wrong on substance, the award fell for procedural reasons:
- Service: The December 1972 party structure notices were not served on the adjoining owners; they were sent only to Mr Johnson. He had no authority to accept service on their behalf. The court upheld the objection: the statute required proper service on the owners. The later forwarding of a copy after the award process had already advanced did not cure the defect.
 - Written appointment: Section 55 required appointments in writing. Mr Johnson had not been formally appointed in writing by these plaintiffs for the dispute arising out of the December notices. Without a valid written appointment, he had no statutory authority to concur in selecting a third surveyor. Therefore Mr Ensom’s selection was itself invalid, and the award was void for want of jurisdiction.
 
The judge emphasised that party wall procedures compulsorily affect proprietary rights; surveyors stand in a quasi-judicial position. The “small details” (proper service, written appointments, validating the third surveyor’s selection) are not technicalities; they are safeguards that must be scrupulously followed. He suggested practical steps: surveyors should inspect each other’s written appointments, ensure the appointment identifies the notice giving rise to the dispute, and third surveyors should verify the written appointments before accepting office.
4) Delivery of the award and practical guidance
The judgment also flagged the importance of knowing when an award is “delivered” - because delivery starts the 14-day appeal clock and defines when works may lawfully proceed. Brightman J did not decide the exact delivery date here (and it was unnecessary to do so), but he urged surveyors to take practical steps so there is no doubt about the date and so that both sides receive the award at the same time.
Outcome
The High Court granted an injunction restraining demolition/reduction of the wall and confirmed that the award was void - both because it purported to authorise an unavailable statutory right and because the procedural foundation (service and written appointments) was missing. Costs were reserved.
Why this case still matters under the Party Wall etc. Act 1996
The 1939 Act has been replaced across England & Wales by the Party Wall etc. Act 1996, which now expressly addresses the reduction of party walls and party fence walls. Section 2(2)(m) grants a right “to reduce, or to demolish and rebuild, a party wall or party fence wall” down to not less than 2 metres, or down to the height currently enclosed upon by the adjoining owner’s building - subject to parapet obligations, costs rules and counter-notice consequences under section 11(7). In other words, what was missing in 1974 is now spelled out.
But Gyle-Thompson remains highly relevant for three reasons:
- Statutory construction discipline. The court insisted that surveyors cannot “create” rights the statute does not give. Under the 1996 Act the award still may “determine the right to execute any work” (s.10(12)), but only within the Act’s four corners. Where surveyors authorise works outside those powers, the award risks being a nullity - and a party may seek relief in the High Court despite the conclusive/appeal provisions.
 - Service and appointment still critical. The 1996 Act likewise demands written appointments/selections (s.10(2)) and sets out service rules (s.15). If a building owner serves the wrong person (e.g., a surveyor without authority), or if an adjoining owner’s surveyor lacks a valid written appointment for the specific dispute, the selection of the third surveyor fails and any award is vulnerable. Gyle-Thompson’s procedural warnings map directly onto the 1996 machinery.
 - Delivery/appeal discipline. The 1996 Act keeps the 14-day appeal window (s.10(17)) and the principle that an award is conclusive unless appealed (s.10(16)). The judgment’s practical advice - synchronised service on both owners, unambiguous recording of the delivery date, and careful file-keeping - remains best practice to this day.
 
Finally, the case serves as a cautionary note about scope creep in awards. Even though s.2(2)(m) now expressly allows reduction in height, awards must still confine themselves to what the Act permits in the circumstances (e.g., minimum heights, parapets, counter-notice effects, and costs apportionment).
Practical implications for today’s projects
- For building owners: Even with a modern right to reduce height, you must serve valid notices (s.3 and s.6 where relevant), appoint surveyors in writing, and ensure any reduction complies with s.2(2)(m) (minimum 2m or to the height enclosed by the neighbour’s building) and s.7 obligations (no unnecessary inconvenience, make good damage). Build your programme around the award delivery date and the 14-day appeal period.
 - For adjoining owners: If you receive an award that appears to authorise works beyond the Act, consider whether it is appealable - or arguably a nullity - and take urgent advice. You retain the right to serve a counter-notice to maintain height at your cost share in certain reduction scenarios (s.11(7)). Keep a close eye on whether you actually received a properly served notice and whether your surveyor was properly appointed in writing for the specific dispute.
 - For surveyors: Follow Gyle-Thompson’s checklist-style guidance. Inspect each other’s written appointments; ensure the appointment identifies the notice giving rise to the dispute; verify authority before selecting a third surveyor; record and simultaneously serve the award on both parties and note the delivery date in writing. Above all, draft awards that determine rights the Act actually confers, not outcomes you might prefer.
 
Key Takeaways - Party Wall Case Law Gyle-Thompson v Wall Street
- No implied right to lower (under 1939 Act). “Demolish and rebuild” did not include reducing a party fence wall’s height; such a change would expropriate a neighbour’s property and required express statutory words.
 - Ultra vires awards are void. Surveyors cannot authorise works the statute does not allow. An ultra vires award can be restrained by the High Court despite conclusive/appeal provisions.
 - Procedural rigour matters. Failure to serve notices on the owners, failure to appoint surveyors in writing, or an invalid third surveyor selection deprives surveyors of jurisdiction and voids an award.
 - Delivery date counts. Surveyors should take practical steps so there is no doubt when an award is delivered, as this triggers the 14-day appeal clock and governs when works may lawfully proceed.
 - Today’s law is different on height - but not on process. The Party Wall etc. Act 1996 now expressly allows reductions in height (s.2(2)(m)) within limits, but Gyle-Thompson’s strict approach to statutory powers, service, appointments, and award validity remains foundational.
 
Conclusion - Party Wall Case Law Gyle-Thompson v Wall Street
Party Wall Case Law Gyle-Thompson v Wall Street is a landmark not because it froze practice in 1974, but because it crystallised the discipline of party wall law: read the statute, do only what it permits, follow the process to the letter, and record the delivery of your award. Under the modern 1996 Act you can reduce a party wall or party fence wall’s height in defined circumstances, but you must still earn that right by proper notice, valid appointments, fair procedure and a tightly reasoned award. If those elements are missing, Gyle-Thompson teaches that the courts will not hesitate to say so.
Get in Touch - Party Wall Case Law Gyle-Thompson v Wall Street
Need help or advice on Party Wall or neighbourly matters?
For advice direct from one of our Surveyors, please call our Enquiry line on 020 4534 3135.
If you would rather we called you instead, please fill in our Contact form and we will be in touch.
For a quick online quote for Party Wall advice, send us the details of your project.
For advice direct from one of our Surveyors, please call our Enquiry line on 020 4534 3135.
If you are planning work that is covered by the Act, or if you have received notice of work from a neighbour and want advice on how best to protect your property please contact:
Geoffrey Adams
BEng (Hons) PgDip FRICS
Senior Director
Party Walls
London
Rickie Bloom
BSc (Hons) MRICS
Senior Director
Party Walls
London
Holly Harris
MRICS, FPTS
Director, Party Wall
Party Wall
London
Henry Woodley
BSc (Hons) MRICS MCIArb FPTS
Director
Party Walls
London