What happens to a party wall notice when 14 days are up?

If Adjoining Owners have given their agreement within 14 days, you can order a schedule of condition (if needed) and commence building works once the notices period expire.

If Adjoining Owners have dissented, the process of reaching an amicable agreement via the production of an ‘Award’ begins.

If after giving them a further 10 days, the Adjoining Owner hasn’t confirmed either way, they are deemed as dissented and a surveyor can be appointed on their behalf to produce the Award.